SANDAG Expenditures as of 07/17/2019
Caltrans Expenditures as of 06/30/2019


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,078,188$1,335,76164.28%48.56%
  I-15 Corridor
$1,403,215$1,307,79093.20%58.41%
  SR 52 Corridor
$503,775$500,13899.28%45.70%
  SR 76 Corridor
$368,820$357,62996.97%64.50%
  Orange Line - Blue Line Corridor
$573,431$572,64699.86%39.62%
  SR 94/SR 125 Corridor
$16,240$8,15550.22%38.36%
  SR 78/SPRINTER Corridor
$487,236$480,35598.59%38.13%
  I-5 North Corridor
$1,647,038$1,000,72360.76%46.72%
  Mid-City Corridor
$44,526$43,84898.48%89.09%
  I-805 Corridor
$685,981$633,77792.39%40.61%
  Border Access Corridor
$976,289$389,35839.88%59.71%