SANDAG Expenditures as of 06/18/2017
Caltrans Expenditures as of 05/31/2017


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,050,964$607,62229.63%43.28%
  I-15 Corridor
$1,414,849$1,266,80689.54%50.48%
  SR 52 Corridor
$514,088$500,15397.29%45.57%
  SR 76 Corridor
$363,908$338,45293.00%60.41%
  Orange Line - Blue Line Corridor
$567,695$568,811100.20%37.91%
  SR 94/SR 125 Corridor
$10,654$9,72691.29%39.73%
  SR 78/SPRINTER Corridor
$480,128$480,07699.99%29.17%
  I-5 North Corridor
$1,306,556$585,55944.82%37.42%
  Mid-City Corridor
$44,478$41,66793.68%77.45%
  I-805 Corridor
$649,939$524,32580.67%35.26%
  Border Access Corridor
$439,724$319,18772.59%49.78%