SANDAG Expenditures as of 02/20/2017
Caltrans Expenditures as of 01/31/2017


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,049,764$510,15824.89%43.00%
  I-15 Corridor
$1,411,538$1,259,74289.25%52.09%
  SR 52 Corridor
$518,010$500,15296.55%45.57%
  SR 76 Corridor
$366,908$328,90689.64%60.77%
  Orange Line - Blue Line Corridor
$568,695$568,49499.96%37.95%
  SR 94/SR 125 Corridor
$10,654$9,72791.30%39.73%
  SR 78/SPRINTER Corridor
$480,128$480,00499.97%29.17%
  I-5 North Corridor
$1,261,281$517,29741.01%35.97%
  Mid-City Corridor
$44,526$40,78791.60%77.45%
  I-805 Corridor
$677,801$511,53475.47%35.36%
  Border Access Corridor
$438,724$315,76871.97%54.86%