SANDAG Expenditures as of 01/23/2017
Caltrans Expenditures as of 12/31/2016


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,049,764$500,13124.40%43.00%
  I-15 Corridor
$1,411,538$1,258,51689.16%52.09%
  SR 52 Corridor
$518,010$500,15296.55%45.57%
  SR 76 Corridor
$366,908$327,54089.27%60.77%
  Orange Line - Blue Line Corridor
$568,695$568,41299.95%37.95%
  SR 94/SR 125 Corridor
$10,654$9,72791.30%39.73%
  SR 78/SPRINTER Corridor
$480,128$479,99599.97%29.17%
  I-5 North Corridor
$1,239,173$510,93241.23%35.97%
  Mid-City Corridor
$44,526$40,72791.47%77.45%
  I-805 Corridor
$677,801$509,53975.18%35.36%
  Border Access Corridor
$438,724$314,08771.59%54.86%