SANDAG Expenditures as of 05/22/2017
Caltrans Expenditures as of 04/30/2017


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,049,764$572,00427.91%42.95%
  I-15 Corridor
$1,396,166$1,264,70190.58%50.48%
  SR 52 Corridor
$518,010$500,15396.55%45.57%
  SR 76 Corridor
$366,908$336,55691.73%60.41%
  Orange Line - Blue Line Corridor
$568,695$568,800100.02%37.91%
  SR 94/SR 125 Corridor
$10,654$9,72691.29%39.73%
  SR 78/SPRINTER Corridor
$480,128$480,06499.99%29.17%
  I-5 North Corridor
$1,245,281$563,65645.26%35.93%
  Mid-City Corridor
$44,526$41,60593.44%79.82%
  I-805 Corridor
$677,801$520,53376.80%35.26%
  Border Access Corridor
$438,724$318,13172.51%49.78%