SANDAG Expenditures as of 11/26/2018
Caltrans Expenditures as of 10/31/2018


Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENDITURE% BUDGET SPENT% WORK COMPLETESTATUS
  I-5 South Corridor
$2,077,988$1,104,57553.16%44.82%
  I-15 Corridor
$1,403,215$1,296,82292.42%58.33%
  SR 52 Corridor
$503,775$500,13899.28%45.70%
  SR 76 Corridor
$368,820$356,44996.65%63.95%
  Orange Line - Blue Line Corridor
$573,431$572,13899.77%39.67%
  SR 94/SR 125 Corridor
$16,240$8,08649.79%38.36%
  SR 78/SPRINTER Corridor
$487,236$480,11698.54%38.13%
  I-5 North Corridor
$1,735,129$871,01650.20%43.54%
  Mid-City Corridor
$44,526$43,80998.39%89.09%
  I-805 Corridor
$684,981$609,02088.91%39.11%
  Border Access Corridor
$976,289$374,25938.33%56.77%