Budget with Green Status
Expenditures as of July 2010

Program: TransNet Early Action Program (P1)
Corridor: (not selected)
Segment: (not selected)    < Back to Previous Screen

Note: All monetary values are in $000s
CORRIDORPHASE DESCRIPTIONBUDGETEXPENSE% BUDGET SPENT% WORK COMPLETESTATUS
  Mid-Coast Corridor (1041500)
$1,282,640.6$51,283.54.00%57.60%
  I-15 Corridor (1201500)
$1,254,567.0$793,329.463.24%88.77%
  SR-52 Corridor (1205200)
$588,622.0$435,557.574.00%13.30%
  SR-76 Corridor (1207600)
$372,908.0$60,372.516.19%59.80%
  Orange Line – Blue Line Corridor (1210000)
$454,194.0$51,758.711.40%0.00%
  North Coast Corridor (1239800)
$214,699.0$109,685.651.09%47.46%
  Mid-City Corridor (1240000)
$53,680.0$2,130.93.97%51.25%
  I-805 Corridor (1280500)
$276,091.0$60,015.021.74%60.64%
  Goods Movement (1300000)
$147,490.0$1,797.01.22%23.13%

 